Professional main focus:
Project management, steering of service providers, Service Management and audit for global IT-infrastructure projects; Data center consolidation; Consultant at the interface IT (networks, DBMS, SAP), economics, chemical / pharmaceutical production, quality assurance
Education:
- Abitur (Great Britain: ~ A-Level, USA: ~ prep school)
- Apprenticeship as industrial trader
- Studies of economics with main focus on informatics
final exams in ' SAP R/3 ', ' software development and maintenance ',
' databases '
degree: Dipl.-Betr. (FH)
Foreign languages:
German: native language
English: fluent
French: fluent
Hardware:
PC: PC-desktop-systems, servers
- Broad knowledge of different hardware standards, but not a specialist for a certain product
- Knowledge of IT in production: PLC-PC-connection, process visualisation, measuring instruments (incl. interfaces)
Products/Standards/Experience:
SAP R/3 MM, SD, BC
Windows Server since NT Server 4 (administration)
All possible Microsoft client software since Windows 3.0; Microsoft Office (all versions) including Microsoft Project, Microsoft Visio
Red Hat Linux 7.2 – 9.B; Red Hat Enterprise Linux since version 4
Red Hat certificates RH033 and RH131
VMWare all versions (including ESXi)
Citrix since Metaframe XP
Microsoft SQL Server since version 7.0 (administration)
Oracle since version 7
SQL
Networking techniques: hardware [cabling, router, switches (Cisco, etc.), hubs, etc.] and all belonging protocols [TCP/IP, http, UDP, IGP (RIP, OSPF), EGP, etc.], OSI-model
IT-Security: architectures (PKI, etc.), protocols (Kerberos, IPSec, https, SSH, etc.), digital signatures, encryption (RSA, DSA, etc.) incl. software (PGP, etc.), certificates, firewalls (hardware, software), virus protection software (eTrust, etc.), etc.
Active Directory, Scripting (Powershell, etc.)
Project management steering of service providers, project planning (technical, time, costs, people), budget planning, budget control, Scrum
Writing of requirements specifications (professional and technical)
Interims management
Audit (FDA audits, supplier audits, customer audits, contact person for auditors), PCI audit, SOX audit
Service Management, Change Management, Release Management
Service Level Agreements (SLAs), Operational Level Agreements (OLAs)
ISO 900x
ITIL V3 Foundation certified (since10/2010)
Prince 2 Foundation certified (since 10/2007)
Projects:
Always:
Further vocational training in CentOS (Red Hat Enterprise Linux) and Windows Server: administration in a heterogeneous environment (including various Windows clients); Oracle; test under VMWare and on bare metal
06/2023 - 12/2023
Project lead
Relocation of a network distribution cabinet in a pharmaceutical production environment
- Analysis of the switch and cable infrastructure of a complete building (408 cables) incl. the connections with the existing production infrastructure (Machines, measuring instruments, laboratory equipment, sensors, etc.; which cable belongs to which component, etc.) and the communication between these components (Switches: IPs, VLANs, Truncs, etc.; Servers: functions, services, etc.)
- Local Hyper-V Infrastructure and global IT infrastructure components
- Detailed technical documentation of all connections and communication relationships together with IT, OT, global network service provider, etc.
- Move strategy
- Writing of the qualification documents together with IT, OT and QA
- Planning:
Building of the new network distribution cabinet (therefor: stearing of external service providers)
Setup of the network distribution cabinet
Switch infrastructure (Design, configuration, etc.)
Rack design (Switches, patch panels, patch boxes, other IT infrastructure, etc.) - Qualification
Move processes
Aligment with maintenance planning , EHS, etc.
Staffing
Project plan
etc.
- Setup of the network distribution cabinet including racking and stacking (therefor: stearing of external and internal service providers)
- Move of the network distribution cabinet: Coordination of the electric service provider; Controlling (cable move and installation, cable measurement, cable patching, cable release, qualification; troubleshooting, etc.)
- Reporting
- Etc.
08/2022 - 05/2023 Family
09/2020 – 07/2022 Pharmaceutical industry
Global LIMS IT architect
- Responsible for the complete technical (re)design of the Labware LIMS IT infrastructure of the SBX, DEV, QAS, PRD instance; project steps:
1. Analysis and stabilization
2. Redesign and implementation
3. Global rollout
- Support of IT QA related topics (writing of IQs, OQs, PQs, SOPs, review of IQ reports, etc.)
- Writing of IT documentation (configuration baseline)
- Change management
- Cutover planning
- Responsible for the reinstallation of all LIMS instances done by the LIMS administrators
- 3rd level LIMS IT infrastructure support
- Steering of service providers (data center, operating system, Citrix, database)
05/2020 – 08/2020 Family
09/2019 - 04/2020 Pharmaceutical industry
Consulting
- Concept study for the development of new methods / procedures in pharmaceutical research
- Data modelling
- Evaluation of the system environment
- Project management incl. taking over of particular project lead tasks in close cooperation with the internal project lead
- Support of the setup of a project team consisting of internal managers
05/2019 – 08/2019 Family
07/2018 - 04/2019 Insurance company
Project lead for international IT projects
- Implementation of the new global network standard in 30+ countries in all geographical regions worldwide
- Disaster recovery planning in 30+ countries in all geographical regions worldwide
System environment: Cisco infrastructure, heterogeneous IT infrastructure, global data center consolidation, steering of service providers
01/2018 – 04/2018 Insurance company
Service management for the European backup infrastructure
- Project lead for several projects, e.g. data center moves of internal customers to the new data centers incl. built up of new infrastructure; from analysis to implementation
- Audit: Preparation and post-processing
- Change management, problem management, incident management (CPI)
- Product lifecycle management (PLM)
08/2017 - 12/2017 Pharmaceutical industry, Austria
Service Management in a pharmaceutical production environment
- Responsible for the performance of all hosting services in Austria
- SPOC for all hosting issues
- Local process manager for service management processes: Incident management, problem management, change management, configuration management, asset management, etc.
- Securing of the introduction / modification of IT infrastructure in a planned, controlled and timely coordinated order
- Coordination of local deliveries and adherence to quality compliance and security standards
- Independent control of suppliers
- Control and steering of technical requests, issues and incidents
- Steering of escalations with the correct support groups within TIS and the suppliers
- Steering of communication
- Securing of the application of IT infrastructure standards, global policies and guidelines
- Follow-up of the migration of local infrastructure and services into the global infrastructure operated by TIS
- Maintenance of the infrastructure inventory and follow-up of required changes in local and global tools
- Proposal for continuous improvement measures
- Coordination of root cause analyses
- Support of audits (preparation, participation and post processing)
- Steering of local infrastructure projects and securing of the implementation of global TIS initiatives (e.g. ramp-up of the ATSC data center)
03/2016 - 06/2017 Pharmaceutical and Chemical industry
Coordination of 2 network projects
- Implementation of the global LAN-standard: Exchange of network hardware in 400+ buildings in 1000+ network distribution cabinets, replacement of copper and fibre optic cabling, etc.)
- Implementation of the global WLAN-standard: Installation of WLAN in 113 selected buildings
- Amount: 1600+ access points and several hundred switches
- Project Management (Rollout including cutover)
- Change Management
- Asset Management including warehouse
- Resource planning and coordination of local IT staff for migration
- Preparation and configuration of HW
- Update of configuration templates
- Update of network design
- Documentation (SOPs, WKIs, etc.), qualification
10/2015 - 01/2016 Pharmaceutical and Chemical industry
Infrastructure Consulting - Perform a study for research labs
- Identification of current lab devices and collection of detailed information about their technical specification and usage
- Analysis of existing processes and used lab instruments.
- Analysis of system interdependencies
- Collection, consolidation and priorization of detailed user and data security requirements, and business critical success factors.
- Security analysis incl. identification of potential vulnerabilities and risks with targeted solution
- Creation of the network design
- Prioritization of implementation steps, based on technical and business need
- Creation of detailed action plan per lab and device
- Definition of a process for introduction of further devices or decommission of old devices.
- Definition of resources, timelines, costs and tasks needed for implementation and related activities.
05/2015 - 08/2015 Software development company
Pre-contractual project management for a software development company specialized on software for law firms
- Aim: Signature of contract with one of the leading law firms in Germany; for this: coordination and creation of all contract relevant parts as follows and leading workshops with the customer
- Professional coordination of 20 rough concepts and detailed concepts for customer specific individual developments, migration procedures, consolidation procedures and interfaces
- Definition of the project organization
- Development of a binding project plan
- Finance, Service Management, etc.
04/2014 – 02/2015 Finance / money transfers
Steering of a team of 30+ offshore software developers and architects in India for the support and enhancement of applications of a payment solutions provider; project management
- Environment: Network for the connection of about 1.000.000 payment terminals, the card issuers, acquirers, other financial institutions, etc. incl. 20+ applications for the transmission and analysis of data
- Service Strategy, Service Design, Service Transition: Change Management, Release Management , Deployment Management, etc.,
- Service Operation (Incident Management, etc.)
- Negotiation of support and development tasks between customer IT and the Indian team
- Process analysis and process improvement
- Quality assurance: steering of quality gates (design review, development review, etc.)
- Data center moves of the applications
- SEPA projects
- Preparation of SOX audits and PCI (Payment Card Industry) audits
06/2013 - 11/2013 Pharmaceutical industry
Preparation of an FDA audit for a pharmaceutical production site
- Virtualized IT environment for the validated production systems; environment contains: MES (Management Execution System), building control, high rack storage, LIMS (Laboratory information and management system), Chromeleon, automatic transport system
- Creation of audit reliable documentation for the IT environment and for new introduced IT services in accordance with local and global standard operating procedures
- Review and creation local standard operation procedure documents with IT involvement to fulfill local quality assurance demands / requirements
- Verification of the qualification status
- Responsible onsite contact for audit related questions by external suppliers, customers, regulatory administration (FDA) and health authorities
- Support of project related corrections and optimizations in the IT environment
- Manage locally provided services and service providers
System environment: Windows Server 2003 /2008, Oracle 10gr2 and 11gr2, Microsoft SQL Server 2005 and 2008, HP Blade Server 460/465, HP EVA, SAN, High availability solutions, disaster recovery, VMWare (Virtual center 5, ESXi 4.1, VSphere Enterprise 4.1), Citrix Presentation Server 4.5
01/2013 - 03/2013 Pharmaceutical industry, Switzerland
Project Analyst for data center consolidation in Switzerland
accountable for
Engineering of application migration solutions:
- Verifies and documents As-Is Components with support from Application Owners or Service Delivery Managers
- Defines Move Approach per Component based on Solution Architect inputs
- Defines To-Be Components with support from Solution Architects
- Documents Special Requirements with support from Solution Architects
- Reviews and fixes move dates based on availability/constrains of Applications Owners and Vendor Delivery Teams
- Creates Application Move Map (AMM) and obtains necessary sign-offs
- Creates Application Move Specification List and Technical Specification List with support from Solution Architects
- Define Application Cutover Plans (ACPs) and obtains necessary sign-offs
- Manage Application Analyst resources allocated to migration activities
- Reviews and approves Application Move Maps (AMMs)
- Reviews and completes Detailed Migration Plans
- Reviews and approves Application Cutover Plans (ACPs)
- Aligns with other Migration Leads and Vendor Delivery Teams the move day activities
- Tracks and manages ACPs along with Vendor MoD (Manager on Duty) during cutover days
- Ensures and facilitates business testing
- Ensures timely sign-off of “Formal Acceptance” documents
- Identify, escalate and manage resolution of migration risks and issues
03/2012 - 12/2012 Energy
Project lead for data center moves of archiving infrastructure, archive migration from IXOS to SAPERION
Phase 1:
- Data center moves of IXOS archiving infrastructure into the internal high security data centers
- Vital systems
Phase 2:
- Archive migration from IXOS to SAPERION of all vital archiving systems
- Steering of the project team, migration activities, cost planning, capacity planning, organization
- Analysis and collection of details
- Review of the migration target environment with the project team and the archive service provider
- Verification of the migration variants and detailed planning of the required migration steps
- Writing of requirement specifications for missing software functions of the SAPERION archiving software
- Coordination and development of a companywide software development process together with SAPERION
- Mapping of the planning at the outsourcing contract and other arrangements
- Writing of project plans
- Planning and implementation of cost reduction programs
- Creation of concepts for risk and quality management for the move and migration of the applications; development of migration strategies for the move of the applications during the maintenance windows together with the system owners
- Coordination and monitoring of the migration activities
- Adjustments of the results with the stake holders (e.g. divisional IT leads, program and project leads, account managers)
- Regular status reporting of the migration packages
01/2011 - 03/2012 Energy
Sub project lead for decentral data center transformation
- Migration of about 220 servers incl. related applications into operation of the service provider (4 subproject leaders)
- Responsible for 23 transformation projects at several sites in Germany
- Business critical systems
- Analysis and collection of details
- Review of the migration target environment with the project team of the service provider
- Verification of the migration variants and detailed planning of the required migration steps
- Mapping of the planning at the outsourcing contract and other arrangements
- Capacity planning, organization and steering of selected resources, migration (doing), cost planning
- Planning and implementation of cost reduction programs
- Architecture consulting
- Creation of concepts for risk and quality management for the move and migration of the applications; development of migration strategies for the move of the applications during the maintenance windows together with the system owners
- Coordination and monitoring of the migration activities
- Technical support of (re)installations
- Adjustments of the results with the stake holders (e.g. divisional IT leads, program and project leads, account managers)
- Regular status reporting of the migration packages
08/2010 – 02/2011 Pharmaceutical industry, Switzerland
Service Delivery Management in the area of 'pharma development and pharma approval’ (regulatory affairs) and 'clinical studies'
- Single point of contact for the Infrastructure Service Manager (ISM) and the Global Head of Enterprise Infrastructure Services for all requests for infrastructure services
- Provide technical advice and translate business requirements into infrastructure solutions
- Service Strategy, Service Design, Service Transition (Change Management, Deployment Management)
- Serve as point of escalation from ISM for issues not resolved by normal channels. Responsible for resolution of service issues not resolved by normal channels
- Ensure that all infrastructure services are delivered in accordance with agreed SLAs and agreed upon project plans. With Service Managers, pro-actively manage, review and monitor performance against the SLA
- Consolidated reporting of service performance to the ISM and IT Infrastructure for Novartis
- Identify continuous improvement opportunities in cost reduction and performance of all existing IT services within the portfolio
- Negotiate with infrastructure Service groups the allocation of infrastructure resources assigned to business projects
- Negotiates and approves key OLAs within the Infrastructure organization as appropriate. Negotiate and approve SLAs
- Provide input into the infrastructure planning and budget processes
- Development of new services
04/2010 – 05/2010 Pharmaceutical industry, Switzerland
Development of global security processes in an outsourced server environment
- Development of a concept for security health check and the interface to patch management (incl. review of parameters, reporting, etc.)
- Etc.
- ~ 7.000 Servers worldwide with TSCM (Tivoli security compliance manager) clients
10/2009 Logistics
Development of security concept for a computing centre / server rooms, etc.
- Development of a concept for a security system of a computing centre / server rooms: actual-value-survey, professional and technical target-value, target/actual-analyses for hardware, software and processes; 5 server rooms with about 500 servers
- Development of a concept for the related incident management
- Writing of the requirements specifications for the implementation of the processes in the ticketing system
11/2008 – 08/2009 Pharmaceutical industry, Switzerland
Service Management, project lead - global service desk integration for offshore business process outsourcing (BPO) partners
- Development of services: integration and improvement concepts for service desks in the area of offshore BPO
- Development and implementation of worldwide standardized service desk processes (incl. related hardware and software)
- Service Strategy, Service Design, Service Transition: Change Management, Release Management, Deployment Management (rollout), etc.
- Service Operation
- Management / coordination of global teams (ca. 50 persons), incl. staffing
- Project planning (time, costs and staff)
- Writing of process documentation, training material, SOW's, SLA's and SOP's
- Project reporting to global instances (account manager)
- Direct collaboration with offshore BPO partners for financial processes, SAP support, SAP production, software development and the service desk provider
- Offshore BPO partners in China, India, Romania and Mexico, service desk provider in the USA
01/2008 – 11/2008: Chemical industry
SAP-test and SAP-quality assurance, SAP-support
- Test in the environment of SAP master data (material, customers, suppliers, etc.),
BW, SLO, Security (Change of user-IDs and passwords, etc.), etc.
- Architecture: central master data distribution system and about 100 SAP-instances worldwide
- Test of functionality, methods, distribution, workflow, etc.
- Work in various sub projects
- Elaboration and writing of the requirements specifications (professional target-value)
- International 2nd level SAP-Support
- Close collaboration with the software development
- Work on incidents, Change requests, PADs, CONFs and OSS
System environment: SAP R/3 4.7 and newer, several areas (Basis, MM, SD, BW, etc.); various customer specific ABAP developments, GSKC, CA Unicenter, ITIL, change requests, Mantis Bugtracker
10/20007 Prince 2 certification
05/2007 – 11/2007 telecommunication industry
Service Management
- Creation of offers for IT-services for a new IT infrastructure for the shifting of about 50.000 users to another company (> 1.000.000 EUR)
- Quality assurance of offers
- Steering of projects
- Creation of OLAs and SLAs
- Coaching of a junior project leader of a security project (group wide malicious code filtering of the network traffic with Bluecoat AV-boxes); preparation of time-, cost- and resource planning; definition of test users for the friendly user tests, coordination of tests
02/2007 - 04/2007 Supplier for the automotive industry
Preparation and planning of a worldwide client software rollout
- Creation of a worldwide hardware and software inventory
- Automated collection, filtering, import in a DBMS and analysis of system information (writing of Powershell-scripts, cmd-scripts, SQL scripts, etc.)
- Checking of hardware and software compatibility
- Planning of rollout steps, etc. (technic, time, costs, etc.)
- Collaboration with the server and the client support
10/2006 – 01/2007 Software development company
Test and quality assurance of security software
- Enterprise-version of an encryption software
- Test of the software on the client and server side (policies, registry, performance, functionality, authentication, etc); analysis and documentation of errors
- Hardware tests
- Development, modification and configuration of test procedures
- Close collaboration with the hardware dependent software development in Germany and foreign countries
09/2006
Training in ‘Red Hat Enterprise Linux System Administration’ (RH 131)
04/2006 – 08/2006 Bank
Changes, 2nd / 3rd level support Citrix Metaframe XP, test
- Implementation of changes in the production environment
- Rebuilding of Citrix-farms (production and test environment)
- Resolving tickets, troubleshooting; data center operation
- Test incl. modification / development of test procedures (Early Morning Check, Disaster Recovery)
- Environment: the worldwide biggest Citrix-environment (here: the European Citrix infrastructure); actual size: ~ 800 Citrix member servers, ~ 400 services servers (e.g. print servers, FINCA-Servers), 22.000 user
- 7*24 Support
03/2006 Retail trade
Cabling rollout
- Rebuilding and new cabling of 19” network cabinets
- Troubleshooting and test of network components
- Drawing up an inventory and documentation of network components
Project lead Germany for a PC-rollout at several sites (part of a European rollout)
- PC rollout of 1300 PCs in a homogenous hardware environment
and a heterogeneous software environment
- Fully responsible for time, costs and technical realisation
- Analysis and creation / modification of business processes
- Control of contract fulfilment
- Interface between external service providers, corporate governance and the French international project leader
System environment: HP hardware, Windows XP, Windows Server 2000, Red Hat Enterprise Linux 4 ES, SLAs, steering of service providers, ITIL
05/2005 – 08/2005 Consulting enterprise
German, french and english 2nd level support for an outsourcing customer in the chemical industry (about 100 servers and 1000 users, whereas 500 are Citrix)
- Troubleshooting of software and hardware problems, network problems, etc.
04/2005 Wholesale trade (logistic centres), north and south of France
Linux server rollout
- Installation of servers in 19" server cabinets, cabling
- Test of hard- and software packages; troubleshooting of hard- and software problems;
- Test of the network; troubleshooting of network problems
03/2005 Assurance company
Notebook-rollout
- Installation of hardware and software packages
- Test and troubleshooting of defective software packages
- Backups
- Configuration of the network (Windows XP as client under Windows Server 2003)
- User training
- General support
02/2005 Chemical industry
Notebook-rollout
- Installation of hardware and software packages
- Test and troubleshooting of defective software packages
- Configuration of the network (Windows XP as client under Windows Server 2000)
- General support
09/2004 – 10/2004 Telecommunication industry
Network administration in a production environment
- Administration of Windows NT 4.0 Server and Windows Server 2000 (15 servers and 500 clients), 1st -, 2nd – and 3rd- level-support
- Preparation of the rebuilding of the plant’s network infrastructure (transition from FDDI to Gigabit Ethernet)
- Network documentation
- Troubleshooting of the network infrastructure (measuring of cables with a Fluke 400, etc.)
- Software distribution (Peacy)
- General support
08/2004 Health Insurance company
Callcenter-rollout
- Building up a call centre
- Installation of hardware and software packages
- Network configurations
Support of a worldwide Windows XP-Rollout (ca. 15.000 PCs)
- Installation of hardware and software packages
- Test and troubleshooting of defective software packages
- Configuration of the network (Windows XP as client under Windows Server 2000)
- Coordination of the centralised hardware delivery and returns of all sites worldwide
06/2003-07/2003: Media industry
Troubleshooting of a CTI environment in an outbound call centre
- Analysis of synchronisation problems in the PBX-infrastructure (incl. WAN area) after lightning strike; elaboration of solution concepts
- Troubleshooting and optimisation of the DBMS installation (Dialler DBs, etc.) and the network infrastructure: Cleansing of the dialler data, optimisation of the backup procedure (Veritas backup system), planning of new cablings
- Reduction of faults in the MIS' and Data Warehouse's source systems data by defining new filtering rules
- Optimisation of the workflow for the delivery of the daily dialler data and the data for the reporting of the call centre statistics created by the Avaya Supervisor
- Configuration of the Avaya-environment: establishing of new ACD by programming new vectors in the Definity ECS (Enterprise Communication Server)
10/2002-05/2003: University of Freiburg, faculty of informatics
Further vocational training in 'IT-Security' and 'Internet databases'
05/2002-08/2002 Specialised plant construction and engineering
Various network projects:
- Change of IP-addresses from class C to Class A (concept, planning and realisation), configuration of a software router
- Planning of a new network cabling in the manufacturing environment (high-voltage current environment)
- Selection, installation and configuration of network hardware (hubs, switches and routers)
- Network documentation
- Server administration; installation of clients and servers (hardware and software)
04/2000-03/2002 Chemical industry
Strategic IT infrastructure project
Project lead 'Replacement of the VAX' in a manufacturing plant of an international group in the chemical industry; ISO 9001 certified plant
Project content: Complete renovation and rebuilding of the plant's IT infrastructure
Applicable to all sub-projects:
heading of various project groups (4-6 people), pre-studies, actual-value-survey, elaboration and writing of the requirements specifications (professional and technical target-value), target/actual-analysis; time and cost planning; project costs: 480.000 Euro (including own cost centre of 100.000 Euro); negotiation with potential suppliers and supplier selection; optimisation of business processes.
Extensive international travels; corporate language: English
Sub-projects:
1. Polymer planning and stocktaking
1.1 Production planning and stocktaking
Implementation of the centralised SAP R/3 PP based group planning into a plant specific machine planning; development of a planning model for the whole plant (including raw materials, additives, packing material, etc.)
System environment: SAP R/3 PP Release 4.5 / 4.6; Microsoft SQL Server 7.0; Windows NT 4.0 Server
1.2 Polymerisation history (process data)
Extension of the possibilities to analyse and represent about 200 different batch related signals (process data) with influence on product quality for the production control and quality control
System environment: Siemens S5 plc, process visualisation software Wonderware INTOUCH; Wonderware
Industrial SQL Server 7.1; Windows NT 4.0 Server
2. Introduction of a laboratory information and management system (LIMS)
Introduction of a LIMS standard software for quality assurance (in the manufacturing environment, the textile laboratory and the chemical laboratory); selection of a LIMS software; verification that software is in accordance with the plants ISO 9000 business processes; verification of interfaces of different measuring instruments, etc.; Replacement of old and selection of new measuring instruments that can be integrated
System environment: various individually developed software, Microsoft SQL Server 7.0; Windows NT 4.0 Server
3. Replacement of the packaging system
Replacement of the local packaging system with the existing development of another plant; testing of prerequisites and required software changes.
System environment: SAP R/3 MM Release 4.5 / 4.6; individually developed software; Siemens S5 plc;
Microsoft SQL Server 7.0; Windows NT 4.0 Server
Other optimisations within the sub-projects:
Rebuilding of the complete plant's network infrastructure (concept, planning and realisation):
- Analysis, testing and renovation of the fibre channel backbone (by external suppliers)
- Changing of the network cabling from coax to twisted pair
- Segmentation of the plants network according to above mentioned projects
- Selection, installation and configuration of hubs and switches
Administration of Windows NT Server 4.0
07/1999-12/1999 IT Consulting enterprise
During the studies of economics with main focus on informatics: diploma on 'Database Marketing in an IT consulting enterprise’
Analysis of the prerequisites for an introduction of database marketing taking in account the existing database an IT infrastructure
- Analysis of functions, processes, process supporting software, data flow, data model; actual-value-survey, elaboration and writing of the requirements specifications (professional and technical target-value), target/actual-analysis
- Analysis of required changes in the data model and the software
- Test of process supporting software
- Selection and testing of data mining methods for the segmentation and selection of customer data
09/1997 – 02/1999 Public sector
- During studies of economics with main focus on informatics: assistant in the computer centre of the faculty; responsible for network administration and end user service
07/1996 – 08/1996 Pharmaceutical industry
- Drawing up a software and hardware inventory of the production facility of the group; about 600 PCs and servers (job during university vacation)
- Development of a Microsoft Access database application for the administration of the of the inventory
- Network administration, end user service
- Development of different applications in the prior programming languages of VBA (Word basic and Excel basic) for the analysis of complaint data
During apprenticeship as industrial trader: rewarded for suggestion of improvement concerning analysis of manufacturing data (development of a prototype for the analysis of production faults, production balances, etc.); the developed prototype was adapted by external programmers and implemented in production
Projekthistorie
Reisebereitschaft
Sonstige Angaben
exali IT-Haftpflicht-Siegel (Sondertarif für Freelancermap-Mitglieder)
Das original exali IT-Haftpflicht-Siegel bestätigt dem Auftraggeber, dass die betreffende Person oder Firma eine aktuell gültige branchenspezifische Berufs- bzw. Betriebshaftpflichtversicherung abgeschlossen hat. Diese Versicherung wurde zum Sondertarif für Freelancermap-Mitglieder abgeschlossen.
Versicherungsbeginn:
01.01.2015
Versicherungsende:
01.01.2025